Integrated in the water supply system of the North Costa Brava
Reduction of the organic matter present in the catchment waters to minimize the formation of tri-halo-methanes due to chlorination.
Includes;
– Civil work; path arrangement (278 ml), equipment shed (40 m2) and auxiliary works in the facilities.
– Installations;
Feeding the equipment from a tap on the inlet pipe and discharge of the product by tap on the outlet pipe of the tank.
Electricity; grounding, powering the equipment. Photovoltaic production system; field 2.2 kWp, inverter, battery 15.7 kWh.
remote control; SCADA integration
Water; stainless tinsmith, emergency shower.
Forced ventilation.
– Equipment;
Preparation of permanganate from the powdered product PROMINENTE IBERIA SA 125 l/h at 1%
Control by turbidity, redox and TOC sensors
Dosing and centrifugal pumps
Level probes
Valve works