Replacement of an industrial floor with settlements of up to 30 cm by a reinforced slab on micropiles.

Area of works: 3,438.50 m²

Main features

  • Work area isolated with a 12 m high sandwich panel partition.
  • Demolition of the existing floor slab.
  • 8,404 linear metres of PAK’s self-drilling micropiles @ 200.
  • Sub-base regrading.
  • Slab reinforcement, concreting and power-floated finish.

Contact

Let's talk about your project.

Tell us what you need and we will get back to you with a proposal.

Privacy Overview
Corpi

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.